Speed tables go in on North Meridian Avenue this week; 71 Street and Indian Creek Drive at Abbott keep FDOT lane closures. Who to call in Miami Beach.

Last checked Nov. 3, 2026. This page is refreshed weekly. Sources: the Florida Department of Transportation (FDOT) District Six Miami Beach project list, its beaches lane closure list, FDOT’s statewide work zone feed, and the City of Miami Beach capital improvement projects and project updates.

Road work in Miami Beach comes from two owners. FDOT District Six runs the state roads: Collins Avenue and Indian Creek Drive (State Road A1A), Alton Road (State Road 907), 41 Street (State Road 112), 71 Street and Normandy Drive (State Road 934), and the Julia Tuttle Causeway. The city’s Public Works Department and its capital projects office handle city streets, water and sewer lines and flood work, which close lanes too.

Who to call

This week

  • Bayshore neighborhood, North Meridian Avenue between Dade Boulevard and West 28 Street: the city scheduled crews to start installing two speed tables this week, the first phase of its Bayshore traffic calming project. Work runs 8 a.m. to 5 p.m. Monday through Friday. The city said traffic patterns may change with temporary closures and detours, and temporary parking restrictions will be enforced. Access to homes and sidewalks stays open, according to the city’s Oct. 30 project reminder.
  • 71 Street (State Road 934), Collins Avenue to Bay Drive East: single lane closures in both directions, off-peak, under the FDOT project below. FDOT’s work zone feed lists them through Feb. 20, 2027.
  • Indian Creek Drive at Abbott Avenue (State Road A1A), North Beach: FDOT’s work zone feed lists signal work from Oct. 19 through Jan. 29, 2027. Crews are installing a new steel mast arm at the northwest corner and new signal heads, cable and overhead signs. Expect lane closures on Indian Creek Drive and a closed crosswalk with a pedestrian detour. The feed says the sidewalk on one side stays open and the work zone speed is 30 mph.

The Normandy Drive right lane closure on Normandy Isle has dropped off FDOT’s work zone feed. FDOT District Six’s beaches lane closure list said “There are no lane closures at this time” when we checked Nov. 3.

State road projects under construction

71 Street, Bay Drive East to Collins Avenue

FDOT started this $2.2 million project in July 2026 and estimates completion in early 2027, according to its project page. The work:

  • High-visibility crosswalks at every intersection from Bay Drive East to Harding Avenue
  • New vehicle and pedestrian signals, signs and pavement markings
  • Curb ramps with detectable warning surfaces, and repaving and restriping
  • A new video detection system for the signals

Lane closures are allowed only off-peak on non-event days:

Direction When single lanes can close
Eastbound 6 p.m. to 7 a.m. Sunday through Thursday nights; 7 p.m. to 8 a.m. Friday and Saturday nights
Westbound 9:30 p.m. to 7:30 a.m. Sunday through Thursday nights; 10 p.m. to 8 a.m. Friday and Saturday nights
Both 9 a.m. to 3:30 p.m., any day
Side streets 9 a.m. to 3:30 p.m. and 9 p.m. to 6 a.m., any day

Two eastbound lanes can close 11 p.m. to 7 a.m. Sunday through Thursday nights and midnight to 8 a.m. Friday and Saturday nights. Questions: Aliyah Gomez, FDOT community outreach, 786-774-9714.

Collins Avenue at 23 Street

A $420,000 FDOT job at the Collins Avenue and 23 Street intersection, started Nov. 3, 2025, replaces the signal’s power supply and wiring, repaves and restripes the intersection, restores the sidewalk and upgrades vehicle detection. FDOT now estimates completion in December 2026, according to the project page. Lanes can close 9 a.m. to 3:30 p.m. every day, 9 p.m. to 5:30 a.m. Sunday through Thursday nights and 11 p.m. to 7 a.m. Friday and Saturday nights. Questions: Sandra Bello, FDOT, 305-510-0827.

Finished: Collins Avenue, Indian Creek Drive and the 41 Street bridge

FDOT’s project page for Collins Avenue from 44 Street to the 4700 block, Indian Creek Drive from 41 Street to 44 Street and the 41 Street bridge says construction was completed in summer 2026. Its lane closures have ended.

Coming next on state roads

  • Normandy Drive, east of Bay Drive West to west of Rue Versailles: repaving, restriping and a new crosswalk on the east side of the Bay Drive West intersection. Construction is set to start in March 2027, according to the project page. Questions: Jeff Baquedano, FDOT, 786-330-2053.
  • Julia Tuttle Causeway bridge rehabilitation: painting, joint, beam and deck repairs, with two lanes kept open each way during deck work. Construction is set to start in June 2027, according to the project page.

FDOT also lists Alton Road, the Venetian Causeway, a Julia Tuttle Causeway study and a Collins Avenue corridor study in its Miami Beach project list.

City projects that close streets

Project What drivers see Source
Bayshore traffic calming Phase 1 is scheduled for the week of Nov. 2: two speed tables on North Meridian Avenue between Dade Boulevard and West 28 Street. Later phases add speed tables, traffic circles and an intersection improvement on West 28 Street, Prairie, Royal Palm, Sheridan and Chase avenues. About seven months in all; weekdays 8 a.m. to 5 p.m. Questions: Gabriella Gonzalez, Mid Beach neighborhood affairs, GabriellaGonzalez@miamibeachfl.gov. Project page
Venetian Causeway water and sewer mains, Phase 2 Water shutdowns are finished and crews are shutting down sewer sections one island at a time, with brief overnight closures of the island drive and one eastbound lane of Venetian Way, 9 p.m. to 6 a.m. The latest posted closures were Rivo Alto (Oct. 22-23) and San Marino and Di Lido (Oct. 27-28). The city now expects full completion by the end of December. Weekday work hours are 7 a.m. to 6 p.m. Questions: 305-907-6748. Oct. 20 update
Pump Station 19, Indian Creek Drive and 69 Street Nightly closures of the intersection, 10 p.m. to 5:30 a.m., began Sept. 22 with detours via Abbott Avenue southbound and Harding Avenue northbound. The project page still gives an expected completion of Oct. 19 and its latest posted update is dated Sept. 21. We could not confirm on Nov. 3 whether the nightly closure has ended. Project page
West Avenue Phase II Road raising and drainage on West Avenue from 8 Street to Lincoln Road, Bay Road and Lincoln Court. Two-week look-ahead schedules are on the project page. Project page

The city sends construction notices by email for each neighborhood; sign up on its Stay Informed page.

What this means for you

  • Bayshore: this week, expect work crews and parking restrictions on North Meridian Avenue between Dade Boulevard and West 28 Street on weekdays.
  • North Beach: allow extra time on 71 Street, especially at night, and expect lane closures at Indian Creek Drive and Abbott Avenue through January.
  • Indian Creek Drive at 69 Street: check FL511 or call the Public Works Control Room before a late-night trip until the city confirms the closure has ended.
  • Mid-Beach: the 41 Street bridge and Indian Creek Drive work zone is finished.
  • Before a big event weekend, check FL511; FDOT holds most closures to non-event days.

More: getting around Miami Beach and who to call at City Hall.

Frequently asked questions

What is the construction on 71 Street in Miami Beach?

FDOT began a $2.2 million project in July 2026 on 71 Street from Bay Drive East to Collins Avenue: high-visibility crosswalks, new signals, curb ramps and repaving. Completion is estimated for early 2027.

When does FDOT close lanes on 71 Street?

Single eastbound lanes can close 6 p.m. to 7 a.m. Sunday through Thursday nights and 7 p.m. to 8 a.m. Friday and Saturday nights; westbound 9:30 p.m. to 7:30 a.m. and 10 p.m. to 8 a.m. Lanes can also close 9 a.m. to 3:30 p.m. any day, on non-event days only.

When does the Bayshore traffic calming construction start?

The city scheduled work to start the week of Nov. 2, 2026, with two speed tables on North Meridian Avenue between Dade Boulevard and West 28 Street. The whole project is expected to take about seven months, with work 8 a.m. to 5 p.m. weekdays.

Is the Collins Avenue and 41 Street bridge work finished?

Yes. FDOT’s project page for Collins Avenue, Indian Creek Drive and the 41 Street bridge says construction was completed in summer 2026.

How do I check traffic on Miami Beach state roads?