A developer wants 146 rental apartments, offices and shops at 1656-1680 Alton Road, empty since Epicure Market closed. The Planning Board hears it Dec. 8.
A developer wants to build 146 rental apartments, five floors of offices and two levels of shops on the empty stretch of Alton Road where Epicure Market used to be. The building would rise to a 14th-floor rooftop with a pool deck.
The project is called 1680 Alton. It sits on the west side of Alton Road between Lincoln Road and 17th Street. The Planning Board hears it at 9 a.m. Tuesday, Dec. 8, at City Hall.
The details come from the application filed Oct. 4 by Alton Ventures Development LLC. Its letter of intent and operations plan are item 8, file PB26-0863, on the Planning Board’s Dec. 8 agenda.
What would be built
New construction would cover 1656, 1664, 1676 and 1680 Alton Road and 1677 West Avenue. Two Lincoln Road properties, 1209 and 1245 Lincoln Road, are part of the same development site, but nothing new is planned on them.
The operations plan lists:
- 146 apartments for rent, from junior one-bedrooms to three-bedrooms
- 45,313 square feet of stores on the first two floors
- 51,194 square feet of offices on five floors, with floor plates of about 9,000 square feet
- a covered breezeway from West Avenue to Alton Road, with outdoor dining and seating
- a padel court open to the public from 7 a.m. to 11 p.m., booked through an app
- a 4,000-square-foot “Blue Zone Hub” on the second floor for wellness classes and workshops, open to the public
- a rooftop amenity on Level 14 for residents, with a gym, coworking space and pool deck
The site has been empty for years. The developer’s letter says Epicure Market, Ace Hardware and Crunch Fitness all closed, and the block became “boarded-up storefronts” for nearly 10 years.
Rentals only, no short stays
The project uses the Alton City Center Overlay, which the City Commission created in September for this block, according to the letter. Its two ordinances, 2026-4836 and 2026-4837, are attached to the application.
The overlay lets a qualifying project build more than the zoning normally allows. In return, the owner must sign a covenant that bans hotel use and any rental shorter than six months and one day. The comprehensive plan amendment allows up to 150 apartments an acre and a floor area ratio of up to 3.5 for qualifying projects. Elsewhere in the same zoning district, the ratio is 2.0 for residential or mixed use.
The letter says the apartments can only be rentals for the next 20 years, with a minimum lease of one year for the next 30 years.
Parking and traffic
No parking is required, the letter says, but the project would provide 364 spaces. The operations plan gives a slightly lower total, 358. Either way, the parking would be:
- surface spaces at 1677 West Avenue
- Level 3 of the garage for store customers, open to the public
- Level 4 for office tenants, open to the public outside office hours
- Level 5 for residents
The developer says Miami Beach residents could park in unused spaces at public parking rates. It has met the Parking Department about how that would work, the letter says.
City planning staff asked the developer to drop a driveway onto Alton Road, according to the developer’s response to staff comments. The developer wants to keep it as a right-in, right-out entrance. Its traffic engineer, Kimley Horn, found that closing it would raise traffic on already congested parts of Alton Road by 15% to 33%, the response says. It also says FDOT had no objection in a preliminary review.
Deliveries would use six loading bays off the Alton Court alley. The code requires nine, so the developer plans to ask the Design Review Board for a variance.
What the Planning Board decides
Any new building over 50,000 square feet needs a conditional use permit as a “neighborhood impact structure.” That is the only question before the Planning Board on Dec. 8. The board can approve, deny or continue it. The loading variance goes to the Design Review Board separately.
What it means for you
- You can speak at the Dec. 8 hearing. The meeting is in the Commission Chambers at City Hall, 1700 Convention Center Drive, and on Zoom. The Zoom link is on the Planning Board agenda.
- The Alton Road driveway is the open question. Staff and the developer disagree on it, and it affects traffic between Lincoln Road and 17th Street.
- Nothing is approved yet. No construction date has been filed. The project still needs Design Review Board approval and building permits after this hearing.